Pre-Shipment Verification

Factory Acceptance Test For Filling, Capping & Labeling Machines

Define samples, test conditions and measurable acceptance criteria before the machine test, then record the result, correct deviations and retest where required.

Download a Blank Packaging Machine FAT Record

Agree the test conditions first, then record filling, cap handling, labeling, sustained output and deviations in one editable workbook. The template contains no prefilled tolerances or passed results.

Free blank template; no email required. A completed record needs agreed criteria, measured evidence and authorized review. It is not a certificate.

Why FAT Matters

Turn “The Machine Runs” Into An Agreed Test Result

A useful factory acceptance test is based on the actual package and intended operating range. Before testing, buyer and supplier should agree which formats, functions, output conditions and evidence are included. The signed quotation, technical agreement and FAT plan remain the governing documents.

Confirm Scope

Match the test to the purchased filling, cap handling, capping, labeling, coding, inspection and conveyor functions.

Use Representative Samples

Provide production-equivalent containers, closures, labels and filling product, or approve a substitute and record its limitations.

Measure Defined Criteria

Agree test method, sample size, tolerance, run duration and evidence before the test begins.

Test Preparation

Information And Samples To Confirm Before FAT

Package Formats

List every container, closure, pump, trigger and label format included in the purchased scope.

Product Behavior

Confirm viscosity, foaming, temperature, particles, corrosiveness and cleaning requirements.

Target Output

Define sustained test speed by format and filling volume, not only a theoretical peak speed.

Utilities

Record required voltage, frequency, compressed air, product supply and other test conditions.

Acceptance Criteria

Agree tolerances for fill, closure, label position, rejects, alarms and line operation.

Evidence & Witnessing

Confirm whether the buyer attends in person, joins remotely or reviews recorded results.

Sample planning: send enough representative material for setup, changeover and a sustained run. Damaged, inconsistent or prototype samples can invalidate the result and should be identified before testing.
Acceptance Matrix

Typical Packaging Machine FAT Checks

AreaWhat To CheckEvidence
Safety & buildGuards, emergency stops, labels, accessible wiring and agreed construction materialsInspection checklist, photos and functional test
FillingFill quantity or weight, repeatability, dripping, foaming and bottle handlingRecorded samples using an agreed measuring method
Cap handlingCap feeding, orientation, placement, tightening or pressing and bottle damageContinuous run, closure checks and reject record
LabelingLabel feed, position, wrinkles, bubbles, container orientation and missing-label responseSample inspection against agreed position tolerance
Line integrationAccumulation, sensors, interlocks, conveyor transfers and start/stop coordinationSustained line run and alarm demonstration
ChangeoverFormat parts, recipes, guide adjustment, cleaning access and operator tasksObserved changeover and updated settings record
DocumentationConfirmed manuals, diagrams, component lists and included spare partsDocument and packing checklist

The exact checks, tolerances, test length and sample quantities must be agreed for the project. Not every check applies to every machine.

Result & Release

Record Deviations And Close Them Before Shipment

Test Record

Record machine configuration, sample format, settings, utility conditions, measured results, videos and attendees.

Deviation List

Describe any result outside the agreed criterion, its impact, corrective action, owner and due date.

Retest & Approval

Repeat affected checks after correction when the FAT plan requires it, then document approval or agreed open items.

FAQ

Factory Acceptance Test Questions

What samples are needed for FAT?

Use representative containers, closures, labels and product, or an agreed substitute, covering the formats included in the accepted machine scope.

Does FAT prove final production output?

FAT evaluates the machine under agreed factory conditions. Final site output also depends on utilities, materials, operators, upstream supply and downstream equipment.

Can FAT be witnessed remotely?

Remote witnessing and recorded evidence can be arranged when agreed in advance. The camera views, documents and approval method should be defined in the FAT plan.

What happens if a criterion is not met?

Record the deviation, identify corrective action, agree responsibility and repeat the affected test before release when required by the accepted plan.

Pre-Shipment Planning

Confirm Critical Spare Parts Before FAT

Use the machine list, change-part drawings and maintenance plan to identify the wear parts, format parts and electrical items that should be confirmed before shipment.

Plan A Testable Project

Send Your Container, Closure, Label & Product Details

We can use your production requirements to discuss machine configuration and a project-specific pre-shipment test scope.

Discuss My FAT Test Scope
Project Evidence Record

What to Record with Your FAT Workbook

This is a blank evidence structure, not a completed customer case. Each project record is populated only with agreed conditions and measured results; customer identity can remain confidential.

Project referenceInternal reference and machine configuration, without requiring a customer name.
Sample identificationContainer, closure, label and product or approved substitute used for the test.
Test conditionsUtilities, settings, format, measuring method, sample count and run duration.
Acceptance criteriaAgreed output basis, tolerances, closure or label checks, alarms and line functions.
Observed resultMeasured values, photos, videos and witness method recorded without marketing claims.
Deviation closureIssue, corrective action, responsibility, retest evidence and release status.
Video limitA machine video shows the visible process and configuration. It does not prove project-specific output, accuracy or acceptance unless the corresponding FAT conditions and record are supplied.